How to lay pavers for a patio or walkway
Installing pavers involves setting accurate levels, preparing a stable compacted base, screeding bedding sand and laying the pavers with consistent joints. For Australian patios and walkways, drainage, edge restraint and base preparation are critical to preventing ponding, settlement and spreading.
Quick answer
To lay pavers for a patio or walkway, excavate the soil, compact 75–100 mm of crushed rock base, screed 20–30 mm of washed bedding sand, lay pavers with 2–4 mm gaps, and compact with joint sand. According to AS 3727.1, pedestrian pavements require a minimum 1:50 fall away from buildings.
- Skill level
- Intermediate
- Time
- 2–4 days for a 15–25 m² area
- Trade
- Building & Construction
- Updated
- 27 November 2026
Tools you will need
- Tape measure, string lines, stakes and marking paint
- Rotary laser level, dumpy level or 1,200
- Shovel, spade, rake, wheelbarrow and mattock
- Plate compactor weighing approximately 60
- Hand tamper for corners and confined areas
- Two straight screed rails, typically 20
- Straight aluminium screed bar at least 2,000 mm long
- Rubber mallet and paver
- Rubber compactor mat suitable for the selected pavers
- Broom, garden hose and watering nozzle
🧱 How to Lay Pavers for a Patio or Walkway
How do you lay pavers for an Australian patio or walkway?
Installing pavers involves setting accurate levels, preparing a stable compacted base, screeding bedding sand and laying the pavers with consistent joints. For Australian patios and walkways, drainage, edge restraint and base preparation are critical to preventing ponding, settlement and spreading.
Residential paving should follow manufacturer requirements and the principles of AS 3727.1 – Residential Pavements. Check council requirements before changing stormwater flow, working near boundaries or constructing over services.
Skill Level
Intermediate — Estimated time: 2–4 days for a 15–25 m² area
⏱️ Skill Level: Intermediate | ~2–4 days
What tools and equipment are required to lay pavers correctly?
🔧 Tools Required
For a one-off project, hiring a plate compactor and wet brick saw is usually more economical than purchasing them. Hire equipment is also more likely to have suitable power, blade capacity and dust controls.
What base materials and sand depths are required under paving?
Allow approximately:
For small edge haunches, a general-purpose concrete ratio of 1:2:3—cement:sand:aggregate—may be used. A 1:1.5:2.5 structural mix should only be used where specified; structural concrete must comply with AS 3600 and may require engineering certification.
Safety Requirements
⚠️ Safety
Step-by-Step Guide
Step 1: 1️⃣ Plan the Layout and Check Approvals
Measure the proposed patio or walkway and draw a scaled layout. Select a paver size and laying pattern that suits the area; stretcher bond, basket weave and herringbone are common options.
Set the paving width to minimise narrow cuts. For example, adjust a path slightly so it accepts full or half pavers rather than leaving cuts narrower than one-third of a paver.
Confirm:
Mark the outer edges using stakes and string lines. Establish the finished paving level before excavation begins.
Step 2: 2️⃣ Excavate to the Required Depth
Calculate excavation depth by adding the compacted base, bedding layer and paver thickness.
A typical pedestrian build-up may be:
This requires approximately 145–180 mm below the finished surface. Add more depth where unsuitable soil must be removed.
Excavate evenly and remove roots, organic material, soft spots and loose soil. Do not lay paving over topsoil, mulch or uncontrolled fill.
Shape the subgrade to approximately the same fall as the finished paving. Avoid relying on bedding sand to create major level changes.
💡 Mark the excavation depth on several stakes rather than measuring from uneven ground each time.
Step 3: 3️⃣ Prepare and Compact the Subgrade
Check the exposed subgrade for soft or pumping areas. Remove weak soil and replace it with compactable crushed rock.
Where clay or soft soil could migrate into the base, install a suitable geotextile separation fabric. Overlap joins by at least 300 mm, or as directed by the manufacturer.
Lightly moisture-condition the subgrade—it should be damp rather than muddy—and compact it thoroughly. Use a plate compactor in overlapping passes, working systematically across the area.
The subgrade must be firm and stable before adding base material. If deep footprints remain after compaction, additional excavation, stabilisation or professional advice may be required.
Step 4: 4️⃣ Install and Compact the Road Base
Place road base in layers no thicker than approximately 50–75 mm loose depth. Spread each layer evenly with a rake, maintaining the required drainage fall.
Lightly wet the material so it is damp enough to bind, but not saturated. Compact each layer with multiple overlapping plate-compactor passes before adding the next layer.
Check levels using string lines, a laser level or a long spirit level. The compacted base should finish consistently below the intended paving level by the combined thickness of the paver and bedding sand.
A straightedge placed across the base should not reveal hollows greater than about 10 mm. Correct low areas with more base material—not loose bedding sand.
💡 Most failed DIY paving can be traced to an under-compacted or uneven base. Spend extra time here rather than trying to correct levels during laying.
Step 5: 5️⃣ Install Edge Restraints
Edge restraints stop the outer pavers from spreading and allow the joints to remain locked.
Suitable restraints include:
Position the restraint accurately along the string line and secure it to the compacted base. If using concrete haunching, keep the concrete low enough that it will be concealed by soil or landscaping while still supporting the lower portion of the edge paver.
Allow concrete restraints to develop adequate strength before final compaction. Avoid placing rigid concrete directly over garden soil or uncompacted fill.
Step 6: 6️⃣ Screed the Bedding Sand
Place washed bedding sand over the compacted base. Set screed rails to achieve a consistent uncompacted layer, usually around 25–30 mm, which will settle during final compaction.
Drag a straight screed bar over the rails using a gentle sawing motion. Fill low spots and repeat until the surface is smooth and follows the required fall.
Remove the screed rails carefully and fill the resulting channels with bedding sand. Smooth them without walking on the finished screed.
Only screed as much area as can be paved that day. Do not compact the bedding sand before laying unless the paver manufacturer specifies otherwise.
💡 Work from the laid pavers rather than standing on the screeded sand. Use a board over the paving to distribute body weight if necessary.
Step 7: 7️⃣ Lay and Cut the Pavers
Begin from a straight, fixed edge such as the house line, a set-out string or installed border. Confirm the first row is square using the 3-4-5 method or by checking diagonals.
Lay pavers gently onto the sand—do not slide them into position or hammer them deeply. Maintain the manufacturer’s recommended joint width, commonly around 2–5 mm. Moulded spacer lugs should not be treated as a substitute for checking alignment.
Check straightness every few rows with string lines. Minor cumulative errors can create visible waves across a large patio.
Leave cutting until most full pavers are laid. Mark each cut clearly and use a wet brick saw for accurate work. Avoid pieces narrower than approximately one-third of a full paver where possible.
For circular drains or obstacles, make several controlled cuts rather than forcing the paver. Keep gaps around drainage fittings neat and consistent.
Step 8: 8️⃣ Compact, Fill the Joints and Finish
Sweep the surface clean before operating the plate compactor. Concrete pavers can generally be compacted with a suitable rubber or polyurethane mat, but always confirm the manufacturer’s requirements. Some clay, large-format or natural-stone products must not be plate-compacted.
Make two diagonal passes across the paving, keeping the compactor moving and staying at least 1 m away from unsupported edges.
Spread dry jointing sand over the surface and broom it diagonally into the joints. Compact again if permitted, then repeat until the joints remain full.
For polymeric sand:
Finish surrounding soil or landscaping below the paver surface so it does not wash onto the paving. Clean the area and test drainage with a gentle hose flow.
Wait for the pavers to dry completely before applying any optional sealer. Some pavers require an initial weathering period, so follow the supplier’s instructions.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
🔧 Recommended Tools
Frequently asked questions
- What is involved in lay pavers for a patio or walkway?
- Installing pavers involves setting accurate levels, preparing a stable compacted base, screeding bedding sand and laying the pavers with consistent joints. For Australian patios and walkways, drainage, edge restraint and base preparation are critical to preventing ponding, settlement and spreading.
- What skill level do I need for lay pavers for a patio or walkway?
- Intermediate — Estimated time: 2–4 days for a 15–25 m² area
- What are common mistakes when lay pavers for a patio or walkway?
- 1. Insufficient excavation or base depth: Thin bases settle, rut and allow pavers to move. 2. Poor drainage falls: Flat or reverse-falling paving can pond water or direct moisture toward the building. 3. Using bricklayer’s sand as a structural base: Bedding sand cannot replace compacted crushed rock. 4. Failing to install edge restraints: Unsupported edges spread, causing joints
- What tools do I need for lay pavers for a patio or walkway?
- This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
- What is the Australian standard for laying pavers?
- The relevant standard is AS 3727.1:2016 (Residential Pavements). This standard specifies structural sub-base depths, crossfall drainage falls of at least 1:50, and edge restraint detailing for pedestrian paths. For projects in Victoria and New South Wales, trade work must also comply with state building regulations regarding stormwater diversion from adjoining boundaries.
- How thick should sand and road base be for a paver patio?
- A pedestrian patio requires 75 mm to 100 mm of compacted crushed rock road base beneath a 20 mm to 30 mm layer of screeded coarse bedding sand. On soft, reactive clay soils, the crushed rock base must increase to 100 mm to 150 mm to prevent structural rutting and paver subsidence.
- Why do pavers need edge restraints in Australia?
- Pavers need edge restraints to stop lateral movement and joint sand wash-out under traffic and rain. Edge restraints consist of trowelled wet-mix concrete haunching or spiked aluminium edging. Unrestrained edges fail prematurely when seasonal moisture changes cause the uncompacted subgrade to shift, leading to severe joint separation.
- Can you use bricklayer's sand to bed pavers?
- No, bricklayer's sand must never be used as bedding sand under pavers. Brickies sand contains clay and fine particles that degrade, retain moisture, and wash out during heavy rainfall. Australian standards require coarse, washed river sand or manufactured bedding sand conforming to AS 2758 to ensure adequate drainage and structural interlock.