How to lay pavers for a patio or walkway

Installing pavers involves setting accurate levels, preparing a stable compacted base, screeding bedding sand and laying the pavers with consistent joints. For Australian patios and walkways, drainage, edge restraint and base preparation are critical to preventing ponding, settlement and spreading.

Quick answer

To lay pavers for a patio or walkway, excavate the soil, compact 75–100 mm of crushed rock base, screed 20–30 mm of washed bedding sand, lay pavers with 2–4 mm gaps, and compact with joint sand. According to AS 3727.1, pedestrian pavements require a minimum 1:50 fall away from buildings.

Skill level
Intermediate
Time
2–4 days for a 15–25 m² area
Trade
Building & Construction
Updated
27 November 2026

Tools you will need

  • Tape measure, string lines, stakes and marking paint
  • Rotary laser level, dumpy level or 1,200
  • Shovel, spade, rake, wheelbarrow and mattock
  • Plate compactor weighing approximately 60
  • Hand tamper for corners and confined areas
  • Two straight screed rails, typically 20
  • Straight aluminium screed bar at least 2,000 mm long
  • Rubber mallet and paver
  • Rubber compactor mat suitable for the selected pavers
  • Broom, garden hose and watering nozzle

🧱 How to Lay Pavers for a Patio or Walkway

How do you lay pavers for an Australian patio or walkway?

Installing pavers involves setting accurate levels, preparing a stable compacted base, screeding bedding sand and laying the pavers with consistent joints. For Australian patios and walkways, drainage, edge restraint and base preparation are critical to preventing ponding, settlement and spreading.

Residential paving should follow manufacturer requirements and the principles of AS 3727.1 – Residential Pavements. Check council requirements before changing stormwater flow, working near boundaries or constructing over services.

Skill Level

Intermediate — Estimated time: 2–4 days for a 15–25 m² area

⏱️ Skill Level: Intermediate | ~2–4 days

What tools and equipment are required to lay pavers correctly?

🔧 Tools Required

Tape measure, string lines, stakes and marking paint
Rotary laser level, dumpy level or 1,200–1,800 mm spirit level
Shovel, spade, rake, wheelbarrow and mattock
Plate compactor weighing approximately 60–90 kg
Hand tamper for corners and confined areas
Two straight screed rails, typically 20–30 mm thick
Straight aluminium screed bar at least 2,000 mm long
Rubber mallet and paver-spacing tools
Brick saw with diamond blade, or 230 mm angle grinder with masonry blade
Rubber compactor mat suitable for the selected pavers
Broom, garden hose and watering nozzle
Screed board, bolster chisel and masonry pencil
Knee pads and paver-lifting clamp

For a one-off project, hiring a plate compactor and wet brick saw is usually more economical than purchasing them. Hire equipment is also more likely to have suitable power, blade capacity and dust controls.

What base materials and sand depths are required under paving?

Concrete, clay or natural-stone pavers, plus 5–10% extra for cuts and breakages
Road base or compactable crushed rock:
75–100 mm compacted depth for most pedestrian patios and paths
100–150 mm where soil is soft, reactive or poorly drained
Washed bedding sand at 20–30 mm compacted finished depth
Dry jointing sand or polymeric jointing sand compatible with the pavers
Geotextile separation fabric where the subgrade is soft, clay-based or prone to mixing with the base
Rigid edge restraints, concrete edging or treated paving borders
Cement, sand and aggregate for concrete edge haunching, if required
Drainage channel, grate or stormwater fittings where surface runoff needs collection
String-line stakes and temporary timber formwork
Paver sealer, optional and compatible with the selected paving

Allow approximately:

Base material: area in square metres × compacted depth in metres × approximately 2.0 tonnes/m³, then add 10%
Bedding sand: area × 0.025 m, then add approximately 10%
Jointing sand: typically 2–5 kg/m², depending on paver size and joint width

For small edge haunches, a general-purpose concrete ratio of 1:2:3—cement:sand:aggregate—may be used. A 1:1.5:2.5 structural mix should only be used where specified; structural concrete must comply with AS 3600 and may require engineering certification.

Safety Requirements

⚠️ Safety

Wear safety glasses, hearing protection, gloves, steel-capped boots, long sleeves and knee pads.
Cutting concrete or clay pavers can generate respirable crystalline silica. Use a wet saw or on-tool dust extraction and wear a correctly fitted P2 respirator. Never dry-cut in an enclosed area.
Plate compactors and saws create significant noise and vibration. Follow the hire company’s operating instructions and take regular breaks.
Pavers and bags of base material are heavy. Use a wheelbarrow, lifting clamp or two-person lift, and keep loads close to the body.
Contact Before You Dig Australia before excavating. Confirm the location of electrical, gas, water, drainage and communications services.
Keep extension leads protected by an RCD and away from wet cutting areas.
Barricade the work zone and keep children and pets clear of machinery, excavations and stacked pavers.
At-ground paving does not normally require scaffolding. If access involves raised edges, retaining walls or falls from height, use compliant platforms, guardrails or scaffolding installed under applicable state WHS regulations.
Do not direct runoff onto adjoining properties or against the house. Check local council and state requirements for stormwater, crossovers and work near easements.
Elevated patios, retaining structures and paving supporting vehicle loads may require engineering certification.

Step-by-Step Guide

Step 1: 1️⃣ Plan the Layout and Check Approvals

Measure the proposed patio or walkway and draw a scaled layout. Select a paver size and laying pattern that suits the area; stretcher bond, basket weave and herringbone are common options.

Set the paving width to minimise narrow cuts. For example, adjust a path slightly so it accepts full or half pavers rather than leaving cuts narrower than one-third of a paver.

Confirm:

Finished paving will remain below the building’s damp-proof course and weepholes—generally maintain at least 75 mm clearance below weepholes unless approved construction details state otherwise.
Paving will not cover termite inspection zones.
Door thresholds, drains, garden beds and adjoining paths remain accessible.
The surface can fall away from buildings, generally around 1:60 to 1:80, subject to site conditions and manufacturer or council requirements.
Water will discharge to landscaping, a lawful point of discharge or a compliant drainage system.

Mark the outer edges using stakes and string lines. Establish the finished paving level before excavation begins.

Step 2: 2️⃣ Excavate to the Required Depth

Calculate excavation depth by adding the compacted base, bedding layer and paver thickness.

A typical pedestrian build-up may be:

50 mm paver
20–30 mm bedding sand
75–100 mm compacted road base

This requires approximately 145–180 mm below the finished surface. Add more depth where unsuitable soil must be removed.

Excavate evenly and remove roots, organic material, soft spots and loose soil. Do not lay paving over topsoil, mulch or uncontrolled fill.

Shape the subgrade to approximately the same fall as the finished paving. Avoid relying on bedding sand to create major level changes.

💡 Mark the excavation depth on several stakes rather than measuring from uneven ground each time.

Step 3: 3️⃣ Prepare and Compact the Subgrade

Check the exposed subgrade for soft or pumping areas. Remove weak soil and replace it with compactable crushed rock.

Where clay or soft soil could migrate into the base, install a suitable geotextile separation fabric. Overlap joins by at least 300 mm, or as directed by the manufacturer.

Lightly moisture-condition the subgrade—it should be damp rather than muddy—and compact it thoroughly. Use a plate compactor in overlapping passes, working systematically across the area.

The subgrade must be firm and stable before adding base material. If deep footprints remain after compaction, additional excavation, stabilisation or professional advice may be required.

Step 4: 4️⃣ Install and Compact the Road Base

Place road base in layers no thicker than approximately 50–75 mm loose depth. Spread each layer evenly with a rake, maintaining the required drainage fall.

Lightly wet the material so it is damp enough to bind, but not saturated. Compact each layer with multiple overlapping plate-compactor passes before adding the next layer.

Check levels using string lines, a laser level or a long spirit level. The compacted base should finish consistently below the intended paving level by the combined thickness of the paver and bedding sand.

A straightedge placed across the base should not reveal hollows greater than about 10 mm. Correct low areas with more base material—not loose bedding sand.

💡 Most failed DIY paving can be traced to an under-compacted or uneven base. Spend extra time here rather than trying to correct levels during laying.

Step 5: 5️⃣ Install Edge Restraints

Edge restraints stop the outer pavers from spreading and allow the joints to remain locked.

Suitable restraints include:

Proprietary aluminium, steel or plastic paver edging
Concrete kerbs
Mortared masonry edging
Treated timber edging for light-duty garden paths
Concrete edge haunching

Position the restraint accurately along the string line and secure it to the compacted base. If using concrete haunching, keep the concrete low enough that it will be concealed by soil or landscaping while still supporting the lower portion of the edge paver.

Allow concrete restraints to develop adequate strength before final compaction. Avoid placing rigid concrete directly over garden soil or uncompacted fill.

Step 6: 6️⃣ Screed the Bedding Sand

Place washed bedding sand over the compacted base. Set screed rails to achieve a consistent uncompacted layer, usually around 25–30 mm, which will settle during final compaction.

Drag a straight screed bar over the rails using a gentle sawing motion. Fill low spots and repeat until the surface is smooth and follows the required fall.

Remove the screed rails carefully and fill the resulting channels with bedding sand. Smooth them without walking on the finished screed.

Only screed as much area as can be paved that day. Do not compact the bedding sand before laying unless the paver manufacturer specifies otherwise.

💡 Work from the laid pavers rather than standing on the screeded sand. Use a board over the paving to distribute body weight if necessary.

Step 7: 7️⃣ Lay and Cut the Pavers

Begin from a straight, fixed edge such as the house line, a set-out string or installed border. Confirm the first row is square using the 3-4-5 method or by checking diagonals.

Lay pavers gently onto the sand—do not slide them into position or hammer them deeply. Maintain the manufacturer’s recommended joint width, commonly around 2–5 mm. Moulded spacer lugs should not be treated as a substitute for checking alignment.

Check straightness every few rows with string lines. Minor cumulative errors can create visible waves across a large patio.

Leave cutting until most full pavers are laid. Mark each cut clearly and use a wet brick saw for accurate work. Avoid pieces narrower than approximately one-third of a full paver where possible.

For circular drains or obstacles, make several controlled cuts rather than forcing the paver. Keep gaps around drainage fittings neat and consistent.

Step 8: 8️⃣ Compact, Fill the Joints and Finish

Sweep the surface clean before operating the plate compactor. Concrete pavers can generally be compacted with a suitable rubber or polyurethane mat, but always confirm the manufacturer’s requirements. Some clay, large-format or natural-stone products must not be plate-compacted.

Make two diagonal passes across the paving, keeping the compactor moving and staying at least 1 m away from unsupported edges.

Spread dry jointing sand over the surface and broom it diagonally into the joints. Compact again if permitted, then repeat until the joints remain full.

For polymeric sand:

Follow the product’s minimum joint width and depth requirements.
Remove all residue from the paver surface.
Activate it with the specified amount of water.
Protect it from rain and traffic during curing.

Finish surrounding soil or landscaping below the paver surface so it does not wash onto the paving. Clean the area and test drainage with a gentle hose flow.

Wait for the pavers to dry completely before applying any optional sealer. Some pavers require an initial weathering period, so follow the supplier’s instructions.

Common Mistakes to Avoid

1.Insufficient excavation or base depth: Thin bases settle, rut and allow pavers to move.
2.Poor drainage falls: Flat or reverse-falling paving can pond water or direct moisture toward the building.
3.Using bricklayer’s sand as a structural base: Bedding sand cannot replace compacted crushed rock.
4.Failing to install edge restraints: Unsupported edges spread, causing joints to open and pavers to rotate.
5.Compacting unsuitable pavers without protection: A bare steel plate can chip, scratch or crack pavers; confirm the manufacturer’s compaction method.

Pro Tips

💡 Order all pavers in one batch and blend units from three or more pallets to distribute natural colour variation.
💡 Set the base parallel to the final surface. Bedding sand should provide a uniform layer, not compensate for an uneven base.
💡 Hire a wet brick saw and plate compactor for a weekend rather than buying low-powered equipment. Purchase is generally economical only for repeated projects.
💡 Keep spare pavers from the same batch for future repairs, especially where colours or profiles may be discontinued.
💡 For large-format pavers, natural stone, driveways, reactive clay sites or areas with drainage problems, obtain advice from a licensed paving contractor or engineer.

Recommended Tools

🔧 Recommended Tools

60–90 kg reversible plate compactor with rubber mat — provides reliable base and final paver compaction.
350 mm wet brick saw with diamond masonry blade — produces cleaner, safer and more accurate cuts than dry cutting.
Rotary laser level with receiver and staff — simplifies finished levels and drainage falls over larger areas.
1,800 mm aluminium spirit level or screed straightedge — useful for checking base flatness and local falls.

Frequently asked questions

What is involved in lay pavers for a patio or walkway?
Installing pavers involves setting accurate levels, preparing a stable compacted base, screeding bedding sand and laying the pavers with consistent joints. For Australian patios and walkways, drainage, edge restraint and base preparation are critical to preventing ponding, settlement and spreading.
What skill level do I need for lay pavers for a patio or walkway?
Intermediate — Estimated time: 2–4 days for a 15–25 m² area
What are common mistakes when lay pavers for a patio or walkway?
1. Insufficient excavation or base depth: Thin bases settle, rut and allow pavers to move. 2. Poor drainage falls: Flat or reverse-falling paving can pond water or direct moisture toward the building. 3. Using bricklayer’s sand as a structural base: Bedding sand cannot replace compacted crushed rock. 4. Failing to install edge restraints: Unsupported edges spread, causing joints
What tools do I need for lay pavers for a patio or walkway?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is the Australian standard for laying pavers?
The relevant standard is AS 3727.1:2016 (Residential Pavements). This standard specifies structural sub-base depths, crossfall drainage falls of at least 1:50, and edge restraint detailing for pedestrian paths. For projects in Victoria and New South Wales, trade work must also comply with state building regulations regarding stormwater diversion from adjoining boundaries.
How thick should sand and road base be for a paver patio?
A pedestrian patio requires 75 mm to 100 mm of compacted crushed rock road base beneath a 20 mm to 30 mm layer of screeded coarse bedding sand. On soft, reactive clay soils, the crushed rock base must increase to 100 mm to 150 mm to prevent structural rutting and paver subsidence.
Why do pavers need edge restraints in Australia?
Pavers need edge restraints to stop lateral movement and joint sand wash-out under traffic and rain. Edge restraints consist of trowelled wet-mix concrete haunching or spiked aluminium edging. Unrestrained edges fail prematurely when seasonal moisture changes cause the uncompacted subgrade to shift, leading to severe joint separation.
Can you use bricklayer's sand to bed pavers?
No, bricklayer's sand must never be used as bedding sand under pavers. Brickies sand contains clay and fine particles that degrade, retain moisture, and wash out during heavy rainfall. Australian standards require coarse, washed river sand or manufactured bedding sand conforming to AS 2758 to ensure adequate drainage and structural interlock.

Written by Bricko, the Building & Construction specialist at WA.Tools.